A Washington HOA can review a solar proposal, but the review begins with the statute that actually governs the community. In November 2026, RCW 64.38.055 remains effective for qualifying homeowners' associations that are still governed by chapter 64.38 RCW, while RCW 64.90.510 governs common interest communities subject to the Washington Uniform Common Interest Ownership Act. The older common-interest statutes are scheduled for repeal on January 1, 2028. Do not use an undated solar policy or assume every Washington community is already under the same chapter.
Open the file with an applicability memo. Record the community's creation date, legal form, declaration, amendments, whether it elected WUCIOA, whether a statutory exception applies, the property or unit involved, the current chapter, counsel's conclusion, and the date verified. RCW 64.90.360 and 64.90.365 contain transition and exception rules that require more care than a simple pre-2018 or post-2018 label.
Keep this HOA checklist from becoming an unsupported condominium rule. RCW 64.38.055 addresses homeowners' associations and does not apply to common areas. RCW 64.90.510 applies to communities subject to WUCIOA and distinguishes a unit from common elements. An older condominium that has not become subject to WUCIOA can require a different analysis under chapter 64.32 or 64.34 RCW and its declaration. Use Washington counsel before extending either solar section to a different legal form.
Determine the proposed location and ownership before discussing appearance. Identify the roof, yard, patio, detached structure, easement, utility area, limited common element, common element, and maintenance responsibility. Obtain the recorded map or plat, declaration, survey, maintenance matrix, photographs, and proposed plans. A resident's exclusive use of an area does not by itself make it owner property or a unit.
RCW 64.38.055 says governing documents may not prohibit a solar energy panel on the owner or resident's property when the panel meets the listed standards. It expressly says the section does not apply to common areas. RCW 64.90.510 says an association may not prohibit a panel on or within a unit when the listed standards are met, and it does not permit an owner to install a panel on or in common elements without board approval. Common-roof and shared-exterior proposals therefore need a property-specific review.
Use a complete application. Request the owner and site, installer and electrical contractor, roof or site plan, elevations, photographs, equipment specifications, mounting method, structural information, array height, roof slope, orientation, frame and visible conduit colors, equipment locations, wiring route, utility, interconnection plan, public permits, warranties, insurance information, maintenance responsibility, expected construction dates, and any requested alternate design.
Record receipt, completeness, questions, professional review, governing deadline, decision meeting, and notice. Ask only for information reasonably connected to the authorized review. Do not keep an application incomplete because a committee prefers a different technology or wants a promise that no future issue can occur.
Verify health, safety, and performance standards through the proper authorities. Both current solar provisions address applicable state and local permitting requirements. They also address certification for solar water-heating systems and safety and performance standards for electricity-producing systems, including the National Electrical Code, IEEE standards, accredited testing laboratories, and, where applicable, Utilities and Transportation Commission safety and reliability rules. The board should request evidence, not perform the electrical certification itself.
Keep association approval separate from public approval. Washington electrical permits and inspections, local building or structural permits, utility interconnection, fire access, and equipment certification belong to the responsible agencies, utility, and qualified professionals. An association approval is not a permit or engineering opinion, and a public permit does not transfer ownership or maintenance duties under the declaration.
Apply roof-profile rules exactly. The statutes allow governing documents to address visibility above the roofline and to condition street-facing roof attachment on conformity with the roof slope and a top edge parallel to the roof ridge. Do not turn those specific allowances into a blanket rule that a panel can never be visible from a street.
Review colors and visible components through the statutory language. The governing documents can require a panel frame, support bracket, or visible piping or wiring to be painted to coordinate with roofing material. Identify the actual visible component, available finish, warranty implications, and requested condition. Avoid requiring paint on equipment when the manufacturer or qualified professional says it would impair performance, listing, or warranty.
Treat ground-mounted shielding as a performance test. The statutes permit a shielding requirement only when it does not prohibit economic installation or degrade operational performance quality by more than ten percent. Request a comparable design and production analysis when shielding is proposed. Preserve the assumptions, method, date, and preparer. Panel count, price, and a visual preference are not a substitute for the statutory test.
Use reasonable placement and manner rules. The governing documents may include other reasonable rules regarding placement and manner. Connect every condition to recorded authority, property ownership, a legitimate association interest, and the current statute. A committee should not create an unpublished setback, neighbor veto, preferred installer, or discretionary ban during a single application.
Review indemnity language with counsel. Both solar provisions allow governing documents to require the installing owner or resident to indemnify or reimburse the association or its members for loss or damage caused by installation, maintenance, or use. Use language authorized by the documents and current law. Do not improvise an unlimited transfer of every roof, weather, insurance, or common-element risk.
Coordinate roof and exterior responsibility. Record who owns and maintains the roof, membrane, flashing, siding, penetrations, conduits, attic, electrical equipment, and access route. Identify warranties, planned roof replacement, removal and reinstallation responsibility, emergency removal, damage repair, inspection access, insurance notice, and resale obligations. Common-property approval should resolve lifecycle responsibility before construction begins.
Evaluate the proposal against the reserve plan and capital schedule when association property is involved. A roof scheduled for replacement in two years creates different costs from a recently completed roof. Estimate professional review, protective work, removal and reinstallation, additional inspection, warranty administration, and future access. Allocate costs only under authority in the declaration, agreement, and law.
Issue a written decision with a traceable basis. Identify the approved drawings and location, each valid condition, public approvals still required, owner obligations, common-property protections, construction access, work hours, closeout evidence, field-change process, maintenance and removal duties, and contact for questions. A denial should cite the exact governing provision, statute, property fact, evidence, and modification that could lead to approval.
Do not use informal neighbor approval as the decision rule. Owners can be notified when the governing documents authorize notice or a construction plan affects access, safety, or common property, but the board remains responsible for the legal decision. A petition, social media thread, or objection based only on appearance is not a substitute for recorded authority and the statutory criteria.
Control construction access. Document contractor insurance, licenses where applicable, staging, parking, roof access, keys, elevator use, fall protection, protection of landscaping and common property, debris removal, outage coordination, resident notice, daily secure condition, damage reporting, and emergency contacts. Association access controls should protect the property without creating a disguised prohibition.
Close the project against the approval. Obtain final permits or inspection records the owner must provide, utility interconnection evidence if applicable, installed photographs, equipment and warranty information, roof or exterior closeout, damage resolution, as-built changes, responsible contacts, and the final maintenance agreement. Do not add new design conditions after installation unless a material deviation or safety issue requires a separate authorized process.
Maintain a resale and emergency record. A future owner, manager, roofer, insurer, utility, and emergency responder may need to know the equipment owner, shutoff, access, warranty, maintenance duty, removal obligation, permit history, and common-property agreement. Store the final record with the lot or unit and the association's affected asset record without publishing private account or security details.
Prepare now for January 1, 2028. The current statute schedule will bring more preexisting communities under WUCIOA as older chapters are repealed. Calendar a legal review of the solar policy, architectural form, decision template, common-element agreement, indemnity language, records, and open applications before the transition. Do not wait for the first 2028 application to discover that the policy cites a repealed section.
Transfer every pending application during a manager, committee, or board change. Deliver the applicability memo, application, plans, deadlines, questions, professional advice, decisions, permits, utility status, construction controls, closeout requirements, open damage claims, and 2028 policy-review calendar. Test that the successor can identify the next action and controlling authority for every open file.
This checklist is general association-management education, not legal, electrical, structural, engineering, permitting, utility, insurance, tax, warranty, or property-specific advice. Washington statutes, transition rules, governing documents, utility standards, codes, and site conditions change. Verify current official sources and use qualified Washington professionals for the actual community and proposal.