A special assessment is not just an invoice. It is a board decision, an owner-ratification process, a funding plan, an allocation calculation, an accounting project, and often the financial foundation for urgent physical work. A Washington condominium or HOA should build those pieces together before it announces an amount or due date.
Washington's Common Interest Ownership Act, or WUCIOA, currently applies its special-assessment ratification procedure to communities within the statute's scope. RCW 64.90.365 applies RCW 64.90.525, along with RCW 64.90.445, 64.90.480(10), and 64.90.502, to communities created before July 1, 2018, with stated exceptions. For those older communities the listed sections do not invalidate existing governing-document provisions, except that RCW 64.90.525 supersedes existing governing-document provisions of plat and miscellaneous communities previously subject to chapter 64.38 RCW. The other sections cited here, including the rest of RCW 64.90.480, RCW 64.90.485, and RCW 64.90.515, are not on that list, so applicability to a particular preexisting condominium or HOA still depends on the community, creation date, governing documents, and transition provisions. Start with current law, the recorded declaration and amendments, bylaws, articles, collection policy, reserve study, and qualified Washington counsel rather than a prior board's template.
Classify the proposed charge before choosing the process. Distinguish a common-expense special assessment from an ordinary annual budget, a charge allocated to fewer than all units under the declaration or RCW 64.90.480, an owner-specific reimbursement or enforcement charge, an insurance deductible allocation, a loan repayment, and an emergency assessment under RCW 64.90.502. Similar-looking invoices can rest on different authority and procedures.
Open one assessment record. Assign a project name and record the condition or obligation, affected components, professional findings, governing-document authority, applicable statutes, reserve-study treatment, current cash and reserve balances, insurance status, estimated cost, alternatives, timing, owner impact, legal review, and responsible board and manager contacts. Use that identifier across bids, minutes, notices, owner accounts, bank activity, invoices, and reports.
Define the need with evidence. For a capital project, preserve inspection reports, photographs, failure history, code or permit requirements, design, scope, useful-life information, bids, contingency, schedule, and consequences of delay. For a judgment, tax, insurance premium, operating deficit, or other obligation, document the amount, deadline, alternatives, and why ordinary cash flow or the existing budget cannot responsibly absorb it.
Test funding alternatives before selecting the amount. Compare available operating cash, reserve funds and any legal or governing-document restrictions, phased work, a bank loan, a line of credit, insurance proceeds, grants or rebates, deferred noncritical work, and a special assessment. Show interest, fees, timing, collection risk, project escalation risk, and future budget effects instead of comparing only the first payment.
Reconcile the proposal with the reserve study and long-range plan. If the work is a reserve component, explain the planned balance, current estimate, timing difference, inflation, prior contributions, and effect on later projects. A special assessment should not hide an unresolved reserve-contribution problem; the board should decide whether future budgets or the reserve schedule also need to change.
Build a complete proposed-assessment budget. Include design and professional services, permits, construction, taxes, insurance, financing costs, temporary services, owner communication, contingency, manager or administration charges authorized by contract, collection allowance, and closeout. Identify what happens if the project finishes under budget or costs exceed the authorized amount.
Calculate allocation from the correct authority. RCW 64.90.480 generally ties common-expense liabilities to the declaration's allocation, while allowing specified expenses to be allocated on other bases when the declaration or statute supports them. Use the current unit schedule, ownership record, declaration provisions, amendments, limited-common-element provisions, and counsel-reviewed methodology. Do not divide the total equally merely because it is easier.
Create an owner-level allocation audit before adoption. For every unit, show the allocated interest or other lawful basis, gross assessment, credits if authorized, installment schedule, rounding, owner name, mailing and electronic notice information, and any pending ownership change. Reconcile the owner schedule to the assessment total and have someone independent of the preparer review the formula.
Prepare the board packet and act at a properly noticed meeting. Include the need, legal and governing-document authority, project budget, alternatives, reserve and financing analysis, owner allocation, installment terms, collection implications, draft owner package, proposed motion, and professional recommendations. RCW 64.90.445 contains current meeting and board-action requirements; use executive session only for a permitted purpose and take required final action in the open meeting.
Draft a motion that can be administered. State the total amount, purpose, allocation basis, owner-level schedule or method, installment dates, early-payment terms, late charges and interest only as authorized, no-fee payment option, treatment of sales and lender requests, project account and reporting, underage or overage treatment, officer authority, and the date and form of the owner-ratification meeting. Avoid delegating every material term to later staff discretion.
Follow the special-assessment ratification procedure. RCW 64.90.525 currently requires the board, within 30 days after adopting a proposed special assessment, to provide owners with a copy of the assessment and schedule an owner meeting to consider ratification. That meeting must occur not less than 14 nor more than 50 days after the assessment is provided. Build the delivery and meeting calendar before the board votes so the association can meet every interval.
Make the owner package understandable and complete. Provide the adopted proposal, purpose, total amount, unit allocation or a clear way to confirm it, installment and payment dates, project scope and timing, funding alternatives considered, reserve or loan effect, meeting date and participation instructions, rejection standard, contact for account questions, and a plain statement that owners should review their own legal, lending, tax, and financial circumstances with appropriate advisers.
Use the statutory rejection standard accurately. Under current RCW 64.90.525, the special assessment is ratified unless owners holding a majority of the votes in the association, or a larger percentage specified in the declaration, reject it at the meeting. A quorum is not required for the ratification meeting. Verify the declaration's threshold, voting allocations, proxies, ballots, remote participation, and meeting procedures with counsel before publishing instructions.
Document the meeting even when rejection is mathematically unlikely. Preserve notice evidence, the owner package, attendance and participation, proxies or ballots, questions and answers, vote tabulation, chair ruling, minutes, and the final ratification result. Do not describe owner silence as an affirmative vote; record the statutory process and whether the required rejection threshold was reached.
Set installment terms that match the project cash curve. RCW 64.90.525 currently permits collection in installments and allows a board to provide a discount for early payment. Compare contractor deposits, progress payments, retainage, financing draws, contingency, and expected delinquencies before setting dates. An installment plan that collects after major invoices are due can force an avoidable loan or project delay.
Offer at least one payment method without a fee as current RCW 64.90.480 requires for assessments. Disclose convenience fees, processing times, check instructions, electronic options, returned-payment treatment, posting order, early-pay discount mechanics, and whom owners should contact before a deadline. Test every payment channel and account code before the first invoice is issued.
Issue the final billing notice through the association's authorized notice methods. RCW 64.90.515 addresses notices to unit owners and the association. Coordinate statutory delivery, governing-document requirements, owner mailing addresses, electronic consent or designation, returned mail, portal publication, and language-access or disability accommodations appropriate to the community. Retain proof of the notice process.
Configure the accounting system before collecting. Create the assessment item, installment schedule, revenue or fund accounts, receivable aging, discount and waiver codes, finance charge rules, payment allocation, bank or lockbox mapping, project class, owner statements, management reports, and reconciliation control. Test a normal payment, partial payment, early payment, returned payment, ownership transfer, credit balance, and delinquency before releasing bills.
Keep project funding visible. Track assessments billed, collections, delinquencies, discounts, financing, investment income, contracts, approved changes, invoices, retainage, contingency, commitments, actual cost, and forecast to completion. The board packet should show both assessment collection performance and project cost performance; a positive bank balance alone does not show whether the project is funded.
Apply the collection policy consistently and lawfully. RCW 64.90.485 currently addresses assessment liens and collection procedures, including notices and limits that require careful current review. Confirm due dates, grace periods, interest, late fees, payment plans, attorney referral, lien action, foreclosure restrictions, owner disputes, bankruptcy, military protections, and communication with counsel. Do not improvise harsher terms for owners who opposed the assessment.
Plan for sales, refinances, and lender questions. Define how the association reports the assessment on resale certificates, lender questionnaires, account statements, payoff or demand information, and estoppel-like requests; whether installments accelerate on sale if the declaration and law allow it; who receives a post-closing bill; and how closing payments are posted. Coordinate the policy with counsel and the association's resale process before the first transaction appears.
Control the funded project through the association's normal procurement and payment safeguards. Use a defined scope, comparable bids when practical, conflict disclosure, contractor verification, written contract, insurance, permits, change-order authority, invoice support, progress review, dual approval, bank reconciliation, lien-release or closeout evidence when appropriate, and board reporting. Assessment approval does not replace contract oversight.
Return to the board and owners when material facts change. A major scope change, cost increase, financing change, allocation error, delayed schedule, insurance recovery, or revised professional recommendation may require a new motion, owner communication, legal review, budget amendment, or additional assessment process. Do not quietly repurpose assessment proceeds or stretch an approved contingency beyond its stated function.
Use the emergency-assessment path only for an actual statutory emergency. RCW 64.90.502 currently provides a distinct process for an emergency assessment imposed by a two-thirds board vote when the statutory conditions are met and restricts proceeds to the emergency purpose. Record the facts supporting the emergency, counsel's advice, vote, notice, fund controls, work, and closeout rather than labeling a long-deferred project an emergency for convenience.
Close both the project and the assessment. Reconcile owner billings and collections, open delinquencies, bank and investment activity, contracts, change orders, invoices, financing, insurance proceeds, contingency, final project cost, warranties, reserve-study updates, and any remaining balance. Adopt and communicate the lawful treatment of a surplus or shortfall and preserve the supporting board decision.
Review the result after completion. Compare the original condition, estimate, schedule, owner allocation, collections, delinquencies, financing, project changes, final cost, complaints, legal expense, and vendor performance with the outcome. Convert lessons into reserve contributions, procurement controls, emergency planning, owner communication, and the next assessment template.
Make the file portable. During a board, manager, accountant, bank, collection counsel, or software transition, transfer the authority, owner schedule, notices, ratification record, payment setup, bank activity, project contracts, open receivables, disputes, financing, warranties, and closeout obligations. The successor should be able to reconcile the assessment total to owner ledgers, cash, project spending, and remaining commitments.
This checklist is general association-management education, not legal, tax, accounting, lending, insurance, reserve-study, construction, collection, or property-specific advice. Washington statutes and WUCIOA applicability, governing documents, owner records, project facts, and court interpretations change. Verify current official sources and use qualified Washington counsel and financial and project professionals for the actual association.