An owner request for one electric-vehicle charger and an association project for shared charging infrastructure are related but different. The owner-request path under Washington law focuses on reasonable restrictions, application review, installation, cost, insurance, maintenance, electricity, and removal. A shared project adds utility capacity, common-element authority, parking design, procurement, incentives, electrical permits, network and billing choices, long-term operations, reserves, and equitable access.
This guide focuses on association-led shared infrastructure for Seattle condominiums and multifamily communities served by Seattle City Light. Use Northland's separate Washington EV charging request checklist for an individual owner's statutory application. Coordinate the two processes so an association project does not leave an owner request unanswered and an owner installation does not undermine a planned shared system.
Start with jurisdiction, utility, and property type. Confirm the parcel, building, number of residential units, parking ownership, condominium or HOA status, City limits, electric utility, meter arrangement, and whether the parking is common, limited common, assigned, deeded, rented, public, or shared with another owner. A Seattle mailing address does not prove Seattle City Light service or City permit jurisdiction.
Check the live Seattle City Light program before budgeting. City Light currently publishes a Multifamily EV Charging program for eligible properties, including condominiums with at least five units, and describes site assessments, infrastructure support, and charger incentives subject to current requirements. Eligibility, funding, equipment, income qualifications, ownership terms, application timing, and incentive amounts change. Use the live program page and actual written offer rather than a prior board presentation.
Identify the authorized applicant. City Light's current multifamily application materials state that for a condominium or other shared-ownership property, the governing body must serve as the applicant and primary contact and must document the governing body's approval and notice to all residents. Confirm the current form, signatory, board authority, owner approval, lender consent, easement, and governing-document requirements before submitting.
Apply before committing construction. City Light's application materials say completed projects are not eligible and that the application must be submitted before the final inspection is completed. Ask City Light in writing which activities may occur before approval, which costs are eligible, who owns installed equipment, how payment or reimbursement works, what inspections and documentation are required, and what happens if the property changes vendors or scope.
Open one controlled project record. Include the governing documents, parking map, electrical drawings, meter and service information, utility bills, owner survey, individual charger requests, board and owner actions, City Light application and offer, site assessment, professional studies, permit record, bids, contracts, equipment submittals, network and billing terms, insurance review, construction evidence, inspections, warranties, operating procedures, and final cost allocation.
Map property and parking rights before design. Record each space, owner or user, common or limited-common status, accessible-space implications, guest and service parking, aisle and route conditions, conduit path, wall and ceiling areas, electrical rooms, utility equipment, easements, fire access, drainage, ventilation, security, and future expansion. Do not promise a charger location merely because a vehicle normally parks there.
Review association authority with counsel. RCW 64.90.405 currently includes association powers relevant to common elements, contracts, improvements, services, and certain EV charging easements or reallocation of common elements. The declaration, survey, plat, articles, bylaws, parking assignments, lender documents, and applicability provisions still matter. Determine whether the project needs board action, owner approval, declaration amendment, easement, space reallocation, or another formal step.
Coordinate individual requests under RCW 64.90.513. The statute currently limits prohibitions and unreasonable restrictions on EV charging in designated parking spaces and sets a process that can include reasonable restrictions, an application, safety and permit requirements, owner costs, insurance, registration, electricity, and maintenance. It also contains a 60-day deemed-approval provision unless the association reasonably requests more information. Use counsel-reviewed intake and do not pause a pending application indefinitely because the board is studying a larger project.
Commission an electrical and utility-capacity assessment. Document existing service, transformers, panels, breakers, feeders, meter configuration, spare capacity, peak demand, load profile, required upgrades, conduit routes, voltage, communication, grounding, ventilation, fire or life-safety interfaces, and expansion options. Ask qualified professionals to compare dedicated circuits, load management, power sharing, new service, and staged buildout.
Do not treat the current panel rating as the whole capacity decision. Building demand, service conductors, transformers, utility infrastructure, diversity, simultaneous charging, future electrification, heat pumps, solar, batteries, emergency systems, and code requirements can affect the design. A network's software limit should not be presented as a substitute for required electrical protection or utility approval.
Choose an operating model before selecting equipment. The board should decide whether chargers will be assigned or shared, resident-only or guest-accessible, association-owned or third-party-owned, networked or locally controlled, billed per session or included in another charge, available around the clock or scheduled, and expanded through a documented queue. The answer affects hardware, contracts, electricity, enforcement, accounting, privacy, and owner expectations.
Verify current City Light equipment requirements. The program currently publishes requirements that differ by charger type and can include approved or vetted equipment, data or usage reporting, networking, installation, and other conditions. Require the utility and vendor to identify the exact eligible model, configuration, software, subscription, communication method, accessibility, and documentation before purchase.
Obtain the correct City electrical permit. Seattle's Department of Construction and Inspections currently identifies EV charging installation as electrical work that requires an electrical permit. Determine who pulls the permit, contractor licensing, plan-review needs, service or utility coordination, inspections, corrections, and final status. A utility incentive approval is not an electrical permit, and an electrical inspection does not decide private parking rights.
Build a common demonstration and bid scope. Give every finalist the same site assessment, drawings, desired capacity, space count, phased expansion, load-management requirement, equipment criteria, utility and permit path, networking, payment collection, accessibility, civil and firestopping work, signage, protection, restoration, testing, training, warranties, data export, and closeout. Require assumptions, exclusions, unit prices, alternates, schedule, and subcontractors.
Evaluate the full cost, not only the charger price. Include design, utility work, transformer or service upgrades, panels, switchgear, conduit, trenching, coring, firestopping, permits, inspections, equipment, bollards, wheel stops, striping, signage, network fees, payment fees, cellular service, electrical energy, demand charges when applicable, maintenance, software support, insurance, replacement, reserves, and administrative time. Show incentives separately until awarded and accepted.
Design a fair cost-allocation policy. Identify which costs benefit the whole property, the charging program, a participating owner, a specific parking space, or future users. Address application fees, installation, shared infrastructure, extensions, electricity, network charges, repairs, damage, nonpayment, removal, and replacement. Obtain legal and accounting guidance before creating assessments, user fees, reimbursements, or owner-specific charges.
Control electricity measurement and billing. Document the meter, rate schedule, interval data, charger readings, network calculation, idle or parking fees, taxes if applicable, refunds, disputes, failed sessions, bad debt, and monthly tie-out. Reconcile charger usage and collections to utility bills and the general ledger. Do not promise that a per-kWh price will always recover every utility and program cost without a current rate and accounting analysis.
Protect payment and user data. Identify what the charger vendor, network, manager, association, and payment processor collect; who can access it; how long it is retained; incident notification; role permissions; multifactor authentication; exports; subcontractors; and termination. Avoid displaying residents' charging histories or vehicle information in public board packets.
Write operating rules before activation. Cover eligibility, registration, space assignment, reservations, time limits, queueing, guest use, accessible use, cables, adapters, prohibited extension cords, damage, outages, snow and maintenance closures, billing, nonpayment, complaints, enforcement, emergency shutoff, and contacts. Review the rules against the declaration, applicable law, fair-housing obligations, parking rights, and the actual system.
Plan maintenance and continuity. Create an asset register with model, serial number, location, circuit, panel, network account, activation date, warranty, vendor, inspection, preventive maintenance, faults, repairs, firmware, subscription, usage, and replacement assumption. Define who responds to a damaged cable, ground fault, water intrusion, collision, vandalism, network outage, billing failure, or recalled component.
Close the project with evidence. Obtain approved plans, permits, final inspection, utility acceptance, incentive documentation, equipment inventory, warranties, manuals, network administrator transfer, access roles, training, test results, as-built drawings, panel schedules, photographs, restoration acceptance, invoices, change orders, releases when appropriate, and board acceptance. Confirm that the installed quantity and model match the approved offer and contract.
Update resale records when required. RCW 64.90.640 currently requires the resale certificate to describe any requirements related to EV charging stations located in the unit or its allocated limited common elements, including application status, insurance, maintenance, and cost information. Build a standardized record for space-specific and shared chargers so future resale responses do not depend on one director's memory.
Report the program to the board. Show available ports, assigned and shared spaces, active users, sessions, energy, revenue or recoveries, utility cost, network and maintenance cost, downtime, open requests, waitlist, faults, incidents, incentive status, capacity remaining, and next capital decision. Use aggregated information where individual detail is unnecessary.
Make the system portable. A manager, board, vendor, network, utility account, bank, or software transition should transfer contracts, applications, permits, as-builts, panel schedules, charger inventory, warranties, network ownership, administrator accounts, payment configuration, user records, billing history, maintenance logs, open cases, utility and City contacts, reserves, and next actions. Test account recovery before removing the departing administrator.
This checklist is general association-management education, not legal, electrical, engineering, utility, fire-code, accessibility, tax, accounting, cybersecurity, insurance, reserve-study, or property-specific advice. Washington statutes, City codes, City Light programs, incentives, equipment, rates, permits, governing documents, and site conditions change. Verify current official sources and use qualified Washington professionals for the actual property and project.